Analysis of the execution of works by direct administration in the District Municipality of Chaglla, Huánuco, Perú

Authors

DOI:

https://doi.org/10.37711/

Keywords:

execution, direct administration, quality, deadlines and budgets

Abstract

The execution of public works constitutes an essential
component for local development and the improvement of municipal infrastructure. In Peru, the direct administration modality allows municipalities to execute projects with their own resources and personnel, seeking to optimize costs and guarantee the quality of the interventions. However, its application requires adequate planning, control, and supervision to avoid technical defciencies, cost overruns, or delays in the deadlines. The objective of this research is to describe the execution of works by direct administration in the District Municipality of Chaglla during the period 2023–2024. Regarding the methods, it was an applied-type study that adopted a quantitative approach
and a descriptive correlational level, using a non-experimental design. The population and the sample were made up of the two works executed under the direct administration modality in the period 2023–2024. Regarding the results, the work “Repair of the backup equipment for archives in the District Municipality of Chaglla, province of Pachitea, department of Huánuco,” had an execution period of 75 calendar days, but it was completed in 69 days. The initial execution budget was S/ 149,133.94, which was used according to what was projected. In relation to the conclusions, the works executed under the direct administration modality in the District Municipality of Chaglla during the period 2023–2024 showed efficient management in technical, financial, and deadline terms. It was verifed that the quality of the labor and materials was adjusted to the specifcations of the technical fle, which demonstrated that adequate planning and supervision allow achieving favorable results in the execution of local public works. 

Downloads

Download data is not yet available.

Author Biography

  • Elvis D. Olivas Timoteo, Universidad de Huánuco

    Arquitecto de profesion , egresado de la Maestria en Gestion publica.

References

Apaico, J. (2023). Análisis del incumplimiento en la ejecución de plazos e incremento de costos en obras por administración directa en la Municipalidad Distrital de Carmen Alto en el periodo 2021 [Tesis para optar el título profesional de ingeniera civil, Universidad Continental]. Repositorio Institucional Universidad Continental. https://repositorio.continental.edu.pe/handle/20.500.12394/13266

Arias, J. L., y Covinos, M. (2021). Diseño y metodología (1.ª ed.). Enfoques Consulting EIRL. https://gc.scalahed.com/recursos/fles/r161r/w26022w/Arias_S2.pdf

Contraloría General de la República. (2024, 14 de febrero). Irregularidades en construcción de puente en Huánuco ocasionaron perjuicio de S/ 4.8 millones. Gob.pe. https://www.gob.pe/institucion/contraloria/noticias/906353-irregularidades-en-construccion-de-puente-en-huanucoocasionaron-perjuicio-de-s-4-8-millones

Decreto Supremo N.° 344-2018-EF. Reglamento de la Ley N.° 30225, Ley de Contrataciones del Estado. (2018, 29 de diciembre). Ministerio de Economía y Finanzas. Diario ofcial El Peruano, 31/12/2018. https://cdn.www.gob.pe/uploads/document/fle/264496/DS344_2018EF.pdf

Figueroa, Y., Alferlyn, A., y Condori, M. (2023). Asignación presupuestaria y la ejecución de gasto público en el contexto universitario peruano. Instituto Universitario de Innovación Ciencia y Tecnología Inudi Perú. https://editorial.inudi.edu.pe/index.php/editorialinudi/catalog/view/142/294/391

Google Maps (2025) Municipalidad Distrital de Chagllag. Disponible en: https://goo.su/5Hueh

Huayra, O. (2021). Control interno en la ejecución de obras por administración directa de la Municipalidad Distrital de Santa María del Valle, Huánuco - 2019 [Tesis para optar el grado académico de maestro en Ciencias Administrativas, con mención en Gestión Pública, Universidad de Huánuco]. Repositorio Institucional UDH. https://repositorio.udh.edu.pe/bitstream/handle/123456789/3649/Huayra%20

Romero%2c%20Oswaldo.pdf?sequence=1&isAllowed=y

Instituto Nacional de Estadística e Informática. (2017). Sector construcción logró resultado positivo por segundo mes consecutivo y en julio creció 3,8%. https://m.inei.gob.pe/prensa/noticias/sector-construccion-logro-resultadopositivo-por-segundo-mes-consecutivo-y-en-juliocrecio-38-9969/

Jumpa, D. C. (2024).Ejecución de obras por administración directa y el cumplimiento de la legislación de gestión ambiental en la Municipalidad Distrital de San Francisco de Cayran, periodo 2020 – 2022 [Tesis para optar el grado académico de maestra en Ciencias Administrativas, con mención en Gestión Pública, Universidad de Huánuco]. Repositorio Institucional UDH. https://repositorio.udh.edu.pe/bitstream/handle/20.500.14257/5142/Jumpa%20Fabian%2c%20Deise%20Carina.pdf?sequence=1&isAllowed=y

Ley N.° 31876. Ley que Regula el Proceso de Ejecución de Obras por Administración Directa a Nivel Nacional. (2023, 21 de septiembre). Diario ofcial el Peruano, 23/09/2023. https://cdn.www.gob.pe/uploads/document/file/5176166/Ley-31876-Ejecuci%C3%B3n%20de%20Obras%20Municipales.pdf

Marín, N. H., Correa, L., y Sotomayor, G. (2020). Relación de la paralización de obras públicas y la crisis política. Ingeniería: Ciencia, Tecnología e Innovación, 7(1). https://doi.org/10.26495/icti.v7i1.1354

Matos, M., Mestre, F., y Torres, O. (2021). Diseño de estrategias para el aprovisionamiento efciente del flujo de materiales en las empresas pymes del sector de la construcción de la ciudad de Cartagena: caso Explanaciones y Construcciones

S.A. Areteus. http://repositorio.unisinucartagena.edu.co:8080/jspui/bitstream/123456789/761/1/Dise%C3%B1o%20de%20estrategias.pdf

Peña, T., y Pirela, J. (2007). La complejidad del análisis documental. Información, Cultura y Sociedad, (16), 55-81. https://tinyurl.com/3psj9ea4

Pinedo, M. (2019). Análisis de las defciencias en obras por administración directa de la Municipalidad Distrital de Shanao, provincia de Lamas, departamento San Martín - 2019 [Trabajo de sufciencia profesional para optar el título profesional de ingeniero civil, Universidad Científca del Perú]. Repositorio Institucional UCP. https://repositorio.ucp.edu.pe/server/api/core/bitstreams/f514f361-9060-4577-bb73-94dd34f55e20/content

Resolución de Contraloría N.° 432-2023-CG. Directiva N.° 017- 2023-CG/GMPL. (2023, 22 de diciembre). Contraloría General de la República. Diario ofcial El Peruano, 29/12/2023. https://cdn.www.gob.pe/uploads/document/file/5623613/4984570-directiva-n-017-2023-cg-gmpl.pdf

Ruiz, F. A. (2021). Análisis de los procesos de contratación y ejecución de obras públicas; determinación y planteamiento de soluciones en sus falencias y áreas críticas de carácter técnico [Tesis de grado previo a la obtención del título de ingeniero civil, Universidad Técnica de Ambato]. Repositorio Institucional UTA. https://repositorio.uta.edu.ec/items/4ef7c581-afe5-4e37-9ea0-5006bc341728

Velásquez, L. (2022). Gestión administrativa y el proceso de ejecución de obras en la Municipalidad Distrital de San Ignacio [Tesis para obtener el grado académico de maestra en Gestión Pública, Universidad César Vallejo]. Repositorio Institucional UCV. https://repositorio.ucv.edu.pe/handle/20.500.12692/92906

Zegarra, J. (2013).Costos y presupuestos en edifcación. Capeco. https://topodata.com/wp-content/uploads/2019/10/Costosy-Presupuestos-en-Edifcacion-CAPECO.pdf

Downloads

Published

2025-07-06